McGill were appointed by W.H. Brown Construction (Dundee) Ltd to carry out the M&E Building Services work for the new build headquarters for The Hillcrest Group Ltd.

As the value of M&E Work Packages was such a large percentage of the overall cost of a project, and having submitted a competitive tender offer for the works, we were quickly engaged by the client to share our experience with the design team and bring value engineering proposals to the table.

Key features:

  • Biomass Boiler Installation
  • Solar Thermal Installation
  • Natural Ventilation
  • Low Energy Lighting
  • Automatic Controls Installation by McGill Controls
  • BREEAM Excellent Rating
Back to Case Studies

Key Facts

Client: The Hillcrest Group Ltd
Contract Value: £1.3m
Principal Contractor: W.H. Brown Construction (Dundee) Ltd
Consulting Engineer: Buro Happold, Glasgow

Gallery

Click image to zoom +
Download document Back to Case Studies