McGill were awarded this full mechanical project by Hadden Construction at Camus House, Carnoustie for Angus Council

This was a full package from design & build to install to commissioning.

There were 16 properties in total – all bungalows.

Works started with installing all copper pipework and drainage.

We then had to install all sanitary ware, combi boilers, kitchen sinks and gutters. 

We finished off by then testing and commissioning all works that had been completed.

After all internal and external works were completed as part of our service we supplied Operation & Maintenance Manuals, Handover packs for the client, and we also had a demonstration with both Hadden and Angus Council of how all the new instalments worked.

Key Features

  • Design & Build
  • Heat Recovery Ventilation units
  • Disabled Access Shower Units
  • Adjustable Height Kitchen Worktops
  • Guttering
  • Leadwork
  • Underground Gas Works
  • Combi-boilers
Back to Case Studies

Key Facts

Client: Hadden Construction
Contract Value: £185,913
Project Duration: 5 months